• Stage two complete

    Six months after starting this project we have hit milestone number two. The wooden decking is removed (bar a few details). A couple of big holes in the deck above the radio officer’s cabinet which has been badly affected by water. Now we can see why. Next stage is to remove all the corrosion before putting down a layer of GRP and resin.

    99% of the deck is up.
    Big holes above the radio officer’s cabin. No wonder it has water damage.